Ames Road Substation Transmission Line Construction

The New York Power Authority is seeking qualified entities to design, furnish, and construct four transmission line segments for the interconnection of National Grid's Ames Rd Substation and NYPA's EP351 and EP352 345 KV transmission lines.

Power Authority of New York WPO Procurement


General
Closed
Q25-7719EE
Dec 10, 2025 04:00 PM
Nov 06, 2025 12:00 PM
Minority-Owned Business (MBE)Service-Disabled Veteran-Owned Small Business (SDVOSB)
Request for Proposal (RFP)
State
Original Solicitation Links
Contact
Edmond Eddings
edmond.eddings@nypa.gov
+19147183869
Power Authority of New York WPO Procurement Category Management 123 Main StreetWhite Plains, NY 10601United States
Description

The New York Power Authority (NYPA) is inviting qualified entities to submit proposals to perform design, furnish, and construct the four transmission line segments required for the interconnection of National Grid's Ames Rd Substation and NYPA's EP351 and EP352 345 KV transmission lines. Two segments will connect to the EP351 transmission line and two will connect to the EP352 transmission line. Each new line segment will consist of two spans. The contract term is 2 years.

Classification Codes
NAICS237130Power and Communication Line and Related Structures Construction
PSCY1MZCONSTRUCTION OF EPG FACILITIES - OTHER, INCLUDING TRANSMISSION
Smart Codes
substation constructiontransmission line designtransmission line constructiontransmission line segments345 kv transmission lineselectrical interconnectionelectrical transmissionpower authority constructionpower transmission linespower substation
Timeline
Nov 06, 2025 12:00 PM-Date of Issue
Dec 03, 2025 12:00 PM-Due Date/Time